Posted on

having jurisdiction approve the plans ….

having jurisdiction approve the plans and issue permits, construction will begin. The date for the pool to be open is April 15.

SoCal Gas started work on underground utilities Nov. 18, and work is complete. Over the next couple of weeks, the meter assembly will be installed for pool equipment.

The COVID-19 crisis has heavily impacted response times by major utilities.

The electrical contractor has a GRF permit and submitted plans to the City of Seal Beach for Mini Farms electrical work and relocating the golf course pump, which is now in the pool equipment room. The City of Seal Beach has sent the plans to a third party for review and comments. They are due back to the city soon.

LEARNING CENTER KITCHEN Work at the Learning Center Kitchen will be complete once the cooktop is installed.

Leave a Reply

Your email address will not be published. Required fields are marked *

LATEST NEWS