POOL PROGRESS

Work continues at the LW pool, which is undergoing a complete renovation. Among the recent progress is:

• Electrical and rough plumbing in women’s and men’s bathrooms continue.

• Rough electrical is being installed for mechanical/attendant room.

• Interior painting of mechanical room prior to setting the equipment.

• Pool area deck drains are being installed.

• Final prepping for Southern California Edison transformer installation.

—Kevin Black, Physical Property Manager