Pool Progress Report
Work on the pool continues at a rapid pace. The HVAC system for the golf starter shack will be completed this week.
Plumbing installation at the pool facility has begun, and roof replacement is nearly complete.
This week, the goal is to complete underground plumbing and check the pressure, with steel installation to begin next week.
Crews will install a network of steel bars, known as