26 January 2022

Share

Work is ongoing with equipment installation set to begin next week

Work is ongoing with equipment installation set to begin next week


POOL UPDATE Work continues at the LW Aquatic Center, which is undergoing a complete renovation. Among recent progress is: • Rough plumbing and electrical inspection have been completed. • Preparation for stucco is being prepared. • Pool decking, along with the area drains, should be completed by Friday, Jan. 28. • Southern California Edison is on track to complete